More than 50,000 m² of noise barriers along 25 km of motorway: foundations, structures and stability checked.
To improve the safety and flow of traffic on the A9, a new through route was built south of Montpellier, with the existing motorway taking local traffic. In the peri-urban area, the project included more than 50,000 m² of noise barriers over 25 km.
THEOREMS carried out the independent review of the construction design of these barriers for the contractor.
Services provided
- Barrier layout, design basis report, general arrangement and detail drawings
- Formwork for foundations and supports, panel layout of superstructures
- Overall stability during construction and in service
- Stability, bearing capacity and resistance calculation notes
- Reinforcement drawings, bar schedules, steelwork anchorages, drilling and splicing